Dubai Precast has secured a full precast building system contract for 93 G+2 townhouses and 2 residential villas at Meydan, Dubai.
The scope of work includes design, supply, delivery and installation services for the project.
The company said it will focus on external sandwich walls, solid walls, columns, beams, stairs, hollow-core and solid slabs, as well as boundary walls.

In total, the order comprises approximately 18,500cu/m of reinforced concrete and 39,000cu/m of hollow-core slabs, it stated.
According to Dubai Precast parent firm, NSL, design works are currently under way with production set to begin soon. The installation work on the Meydan project is targeted for completion by Q4 2026.